TurnKey Projects

Juthor Paper Manufacturing Company
Scope of work:

Construction, Supply ,installation and Testing & Commissioning of Juthor Paper Manufacturing Company
Civil, Erection of PEB Building, Architectural & Finishing, Electro-Mechanical, HVAC System, Firefighting, and infrastructure works.

Type of Contract: Turnkey
Total Area: 9,700 m2
Status: Ongoing
Completion Year: 2023
Client: MEPCO

Industrial Factories - Modon
Scope of Work :

Construction, Supply, installation, and Testing & Commissioning of(84 Industrial Factories) MODON-
Civil, Erection of PEB Building, Architectural & Finishing, Electro-Mechanical, Fire Fighting, infrastructure works. CCTV, Data, and Telephone
Works.

Type of Contract : Turnkey
Total Area : 18,900 m2
Status : Ongoing
Completion Year : 2023
Client : Modon

Al-olyan Show Room
Scope of Work :

Construction, Supply, Installation, Testing and Commissioning of Olyan Company Civil, Erection of PEB Building, Electro-Mechanical,
Architectural & Finishing,, HVAC System, Fire Fighting and Infrastructure Works and Low Current Works.

Type of Contract : Turnkey
Total Area : 6,000 m2
Status : Ongoing
Completion Year : 2023
Client : OlyanCompany

Petronash Arabia Factory
Scope of Work :

Construction, Supply, Installation, Testing and Commissioning of Petronash Arabia Factory Civil, Erection, Electro-Mechanical,
Architectural & Finishing, , HVAC System, Fire Fighting and Low Current Works.
Type of Contract : Turnkey
Total Area: 7,000 m2
Status : Finished
Completion Year : 2021
Client : Petronash Factory.

Yanbu Gate RC
Scope of Work :

Supply and construction of Main Building,
Accommodation Building, Multipurpose Building, Guard Room Building; Mosque, Checkpoint,
Guardhouse and Shade Building,
Fuel Tank with Pumps & Site Works .

Type of Contract : Turnkey
Total Area : 4,000.00 M2
Duration : 12 Months.

Sedra Factory Company ( SLC)
Scope of Work :

Construction, Supply, installation, and Testing & Commissioning of Sedra Medica Factory Company
Civil, Erection of PEB Building, Architectural & Finishing, Electro-Mechanical, Fire Fighting, infrastructure Works CCTV and Data work.
Type of Contract : Turnkey
Total Area : 7,800 m2
Status : Finished
Completion Year : 2022
Client : Sedra Facory Company.

ALSHAEIR Pharma Factory
Scope of Work :

Civil, Steel Structure Erection, Architectural & Finishing, Electro-Mechanical, HVAC System, Firefighting System and Site Development Works
Type of Contract : Turnkey
Total Area : 12,500 M2
Status: Finished

Olayan APPCO Factory
Scope of Work :

Building with all finishing work aluminium cladding elevation, Supply, and erection of PEB Building factory, site work included drainage system, Asphalt work and supply & install fence around the factory All electro – mechanical work
inside the factory (Electrical, fire system.
Plumbing)
Type of Contract : Turnkey
Total Area : 5,000 M2
Completed Year : 2018

Safami Fabricated Metals
Scope of Work :

(Steel structure); Admin Building. Labour
Accommodation, Masjid, and Accessories Bldg.
(Concrete Work + Finishes); Electro-Mechanical
Work (Electrical, fire system. Plumbing and
HVAC) and Site Work.
Type of Contract : Turnkey
Total Area : 17,500 M2
Completed Year: 2017

ITAG International Factory -Jubail
Scope of Work :

Supply & Erection of PEB Building, Electromechanical, Fire fighting, HVAC System, Infrastructure Works, CCTV system.
Type of Contract : Turnkey
Total Area : 8000 M2
Completed year: 2017